Engineering & Construction

Projects Under Design

Project Name City Project Type Location Estimated Construction Period
Apple Blossom LnAlexandriaWater Main ReplacementRiley Rd to end of streetFebruary 19, 2024 to April 4, 2024
Campbell County 16" CCAlexandriaWater Main ReplacementWoeste Rd to Alexandria PkSeptember 18, 2023 to February 29, 2024
Donaldson RdErlangerWater Main RelocationCherry Tree Ln to Mineola PkMay 1, 2023 to September 30, 2025
East 1st StreetSilver GroveWater Main ReplacementFour Mile Rd to Maple StMarch 4, 2024 to April 18, 2024
Gloria Terrell DriveWilderWater Main ExtensionRosewood Drive to Plum StreetNovember 27, 2023 to February 29, 2024
Independence TankIndependenceTank Painting11574 Water Tower WayMarch 1, 2024 to May 1, 2024
Kentaboo AveErlangerWater Main ReplacementDixie Highway to Boone Co LineDecember 4, 2023 to March 15, 2024
KY 236HebronWater Main RelocationDonaldson Road to I-275June 1, 2022 to TBA
KY 536IndependenceWater Main RelocationBristow Road to Boone County LineSpring 2022 to Spring 2024
Meter ReplacementAll CitiesReading System ReplacementEntire Service AreaOctober 2021 to January 2025
Monte CasinoCovingtonWater Main ReplacementHighland Avenue to end of Tower DriveFebruary 12, 2024 to July 11, 2024
Montgomery DrErlangerWater Main ReplacementDixie Highway to Russell McClureMarch 1, 2024 to April 10, 2024
North ReservoirFt ThomasReservoir RestorationMemorial Parkway Treatment PlantNovember 1, 2023 to May 31, 2024

Current Projects

Northern Kentucky Water District
pipe 001

Standard Drawings 2021

View a Specific Subject

General Specifications for Water Mains

Standard Specifications and Drawings for the Installation of Meter Pits